Road Project On Honoco Road

We are starting the process of road work on Monday, June 18th. I do not anticipate any delays on the road other than waiting for some equipment to move at least through Wed. The road will be open and traffic can pass. Possibly Wed afternoon the paving will start at the very south end of the road. Again, this should not have much effect on traffic. Once we move the operation past Deer Trail we will be posting when this is open on both this web site and in emails out. We are looking at about 4 days to pave, Once that is complete we will start the oil and stone project. Please check your emails and this site for specific information.